Submit a ticketCall us

Solarwinds & Cisco Live! Barcelona
Join us from the 29th of January to the 2nd of February at Cisco Live 2018 in Barcelona, where we will continue to show how monitoring the network with SolarWinds will keep you ahead of the game. At our booth (WEP 1A), we will demonstrate how SolarWinds network solutions can help. As a bonus, we are also hosting a pre-event webinar - Blame the Network, Hybrid IT Edition with our SolarWinds Head Geek™, Patrick Hubbard on January 24th - GMT (UTC+0): 10:00 a.m. to 11:00 a.m. There's still time to RSVP.

Home > Success Center > Network Performance Monitor (NPM) > Stack monitoring issue: Unable to construct the data ring diagram because the information required to show the diagram is missing or is not complete

Stack monitoring issue: Unable to construct the data ring diagram because the information required to show the diagram is missing or is not complete

Created by Kevin Twomey, last modified by Aileen de Lara_ret on Jul 14, 2016

Views: 828 Votes: 0 Revisions: 2

Overview

This article provides brief information on the following error:

Unable to construct the data ring diagram because the information required to show the diagram is missing or is not complete.

Stack Monitoring not working on more than 2 switches. 

Environment

NPM version 12.0

Cause 

This is a Cisco bug. 

Resolution

Upgrade the device IOS.

 

 